Project MR533/TJ000201/GLM - Activities implemented for April, May and beginning of June 2008

The continuation of the work on the construction of the channel from Dariyakul Lake to Hudoykul channels:

1. Preparation for transportation and repair of the excavator dragline-652. - Duration - 7 days.
2. Transportation of the excavator on trailer. – Distance 120 km. (there and back) – duration - 1 day
3. Work on the construction of the channel - sinking 0.7 km. – duration 15 days
4. Delivery GSM to place of work- 7 days. – Distance - 30 km h 7 days = 210 km
5. Transportation of technical staff to the place of work (there - back) daily. - distance 15 km. total 150 km.
6. Transportation of the excavator dragline - 3211 (marsh) on trailer. The distance 140 km (there and back). Duration - 1 day.
7. The work on the construction of the channel. Sinking – 0.8 km.

 

 
Статьи
Опрос
Готовы ли Вы участвовать в развитии проекта?

Да
Нет
Отчеты
Скачать файлы
Вид из космоса
Вид из космоса
© 2007—2008 Официальный сайт заповедника «Тигровая балка» - Светлана Благовещенская

[Обратная связь с администрацией]